What is a estimated work remaining?
speech
następna
poprzednia
Estimated work remaining is the number of hours that a team member estimates remain to be worked on any task. This estimate is updated at the end of every day the sprint backlog task is worked on. The estimate is the total estimated hours remaining, regardless of the number of people that perform the work.